Site Progress Update Frome

Another busy week on site this week. From the photos you will see that we have the rafters to the extension on and the rooflight openings formed. The battening out of the kitchen walls and ceiling has been completed and we will be temporally waterproof very soon! The double garage walls are up to plate height and the stud walls have been formed to the two offices. The fascia's and rain water goods have been replaced to the main house as well. In the coming week lots more progress to come with the extension to be first fixed with electrics and plumbing, extension roof to be tiled, garage gables built, roof trusses installed and tiled. It's starting to look great!

Be sure to look in next week for the for a further progress update.

Temporary waterproofing to the windows.

Roof trusses on and rooflight openings formed.

Timber frame office walls and roof trusses taking shape.